BK-STROY developer digest: August 2026

August 2026 for BK-STROY: 3 apartments sold (net increase −54), completion due by year-end for 2 projects. Sales by residential complex and city, new projects, completion dates, unsold stock and ranking among developers, according to the state register of shared-equity construction.

← July 2026 · September 2026 →

Key takeaways

Cancellations and corrections

For one property, developers reduced the number of sold apartments by a total of 57. This is due to contract terminations or corrections in the registry; therefore, the net increase (−54) is lower than the gross increase (3).

Supply runway

Чистого прироста продаж по реестру нет (новых продаж — 3), а нераспроданных квартир — 4 848.

Sold-out rate

BK-STROY’s sell-through is 10%, 21 pp below the national average (31%).

Completion date

Two projects with 239 apartments are scheduled for completion by the end of the year; 237 of these units remain available. Buyers of these apartments will receive their keys sooner, though the developer reserves the right to extend the completion deadlines.

Protection schemes

78% of BK-STROY projects are being built with second-tier bank (BVU) participation, 22% with a KHC guarantee and 0% under an akimat permit (MIO).

Salemdom AI commentary

Monthly Highlights

In August 2026, BK-STROY marked 3 apartments as sold in the state register of shared-equity construction, but at 1 project the number sold fell by 57. The net increase was −54, below July, when it was −19. In the new-sales ranking, the developer placed 31st among 40 companies, down from 21st place the previous month.

Who was selling

August’s sales were recorded in a single residential complex. The leader was MZhD 21, where +3 apartments were sold. The project’s sell-through currently stands at 98%, with 3 of 193 apartments still on sale.

Supply: new objects and remaining stock

Новых объектов в реестре за месяц не появилось. Всего у БК-СТРОЙ 32 объекта, из которых 20 относятся к классу комфорт, 11 к эконому и 1 к бизнесу. В продаже остаётся 4 848 квартир, общая распроданность составляет 10 %. Больше всего непроданных вариантов — двухкомнатные квартиры в количестве 1 901.

Risks and what to check

Buyers should check completion dates: by the end of the year, the planned date falls due for 2 projects with 239 apartments (MZhD Bereke 19 and MZhD Bereke 20), 237 of which are still unsold. Also note the decrease of 57 in the number of apartments sold at one project. Protection schemes are distributed as follows: 78% of projects are being built with BVU participation, 22% with a KHC guarantee and 0% under an MIO permit.

Takeaway for buyers and investors

For investors and buyers, the main options for getting keys quickly are projects due for completion in September and October 2026. Only 3 apartments are left at MZhD 21, so a quick decision is needed if a suitable layout is available. BK-STROY’s overall Salemdom score based on state register facts is 66.6 out of 100.

Commentary prepared by Salemdom AI strictly from the issue's figures.

Monthly Highlights

From 1 to 31 August 2026, according to the state register of shared-equity construction, BK-STROY marked 3 apartments as sold; at 1 project the number sold decreased by 57, for a net increase of −54.

У БК-СТРОЙ в реестре 32 объекта — 31 ЖК: 5 361 квартира, из них продано 513 (10 %), в продаже остаётся 4 848.

No new properties have been added to the registry this month.

Where BK-STROY ranks among developers

By new sales in August 2026, BK-STROY ranks 31st among 40 developers with sales in the register; a month earlier it was 21st.

Salemdom score based on state register facts: 66.6 out of 100; 32 projects in the register in total, the first one about 7 years ago. The score is based on register facts: scale, experience, timelines, demand, transparency and oversight; the BVU, KHC and MIO schemes count equally.

Sales dynamics

For July 2026, BK-STROY's net sales increase was −19 (gross — 10); for August 2026 — −54 (gross — 3). The comparison covers the same projects that were in the register in both months.

Weekly sales fluctuated: the peak occurred between August 8–14 (−2). Developers often record transactions in batches, meaning weekly spikes reflect administrative processing rhythms as much as actual demand.

WeekNet sales growth
August 1–7−5
August 8–14-2
August 15–21−3
August 22–31-44

BK-STROY's best-selling residential complexes

Ranking by increase in sold apartments in the registry for August 2026. These are transactions recorded by the developer in the registry; the contract date and the registration date may differ by a few days.

ЖКDeveloperDistrictSold this monthRemaining
МЖД 21БК-СТРОЙ—+33

Sales leaders: details

MJD 21 (BK-STROY) — +3 apartments sold this month. Sold-out rate — 98%, 3 out of 193 remaining. Payment plan: KZHК. Registry class: economy. Next scheduled handover — March 2027.

New listings

No new BK-STROY projects were added to the register in August 2026.

Completion date

As of August 2026, there were no scheduled completion dates.

Two more projects with 239 apartments are due for completion by the end of the year, with 237 units still unsold. The next deadlines are:

ЖКDeveloperScheduled completionApartmentsNot sold
Bereke 19 Residential ComplexБК-СТРОЙSeptember 2026120118
Bereke 20 Residential ComplexБК-СТРОЙOctober 2026119119

Homebuyer protection schemes

78% of BK-STROY’s projects are being built with second-tier bank participation (BVU), 22% with a Kazakhstan Housing Company (KHC) guarantee and 0% under an akimat permit (MIO). New sales this month: BVU — 0, KHC — 3, MIO — 0.

SchemePropertiesNet sales growth
Bank involvement (Second-tier banks)25−57
KZHIK Guarantee7+3
Akimat (local executive body) permit00

Housing classes

By the class stated in the register, most BK-STROY projects are comfort (20 projects). The register class is set by the developer under the state comfort standard; the marketing class in a complex's advertising may differ.

ClassPropertiesNet sales growthApartments remaining
Comfort Class2003 416
Economy class11-541 277
Business class10155

Room count: sold and remaining

Больше всего непроданных квартир БК-СТРОЙ — двухкомнатные: 1 901. Быстрее распродаются однокомнатные: продано 9 %. Данные о комнатности — из реестра на 10 октября 2026; площадь — типичный диапазон по объектам (медиана и половина объектов вокруг неё), без ошибок ввода.

RoomsApartmentsSoldRemainingSold-out rateTypical area
11 8731631 7109 %38.4 m² (36.3–41.8)
22 0651641 9018 %57.3 m² (57.3–61.5)
31 251821 1697 %82.5 m² (72.4–86.7)
415621541 %113.6 m² (113.6–126.1)
5+160160 %—

Selling out fast

BK-STROY residential complexes where more than 80% of apartments are sold and sales continued this month. Little stock is left, so if a layout suits you, it's better not to put off the decision.

ЖКDeveloperSold this monthSold-out rateRemaining
МЖД 21БК-СТРОЙ+398 %3

Frequently asked questions

How many apartments did BK-STROY sell in August 2026?

According to the state register of shared-equity construction, BK-STROY marked 3 apartments as sold; at 1 project the number sold decreased by 57, for a net increase of −54.

Which BK-STROY residential complexes sold best in August 2026?

Residential Complex 21 — +3. The figures represent the monthly increase in apartments sold in the registry.

Which new BK-STROY residential complexes appeared in August 2026?

No new properties were added to the registry in August 2026.

How many apartments does BK-STROY still have for sale?

По реестру не продано 4 848 квартир из 5 361 (распроданность 10 %).

Which BK-STROY new builds are due for completion by the end of the year?

Two projects featuring 239 apartments are scheduled for completion: Bereke 19 in September 2026 and Bereke 20 in October 2026. These are estimated dates and may be subject to extension by the developer.

What share of BK-STROY new builds is being built with bank participation?

78% of projects involve a second-tier bank, 22% have a KHC guarantee and 0% are built under an akimat permit. Each residential complex's scheme is shown on its page in the “Guarantees” section.

Are there any new entries for BK-STROY in the list of unscrupulous developers?

No new entries for BK-STROY appeared in the official list of unscrupulous developers in August 2026.

Where does the digest data come from?

From the state register of shared construction (homeportal.kz). Salemdom saves a complete snapshot of the register daily; this digest compares the snapshots from July 31, 2026, and August 31, 2026. Prices are taken from developers' catalogs on Salemdom.

How to buy a new-build apartment from BK-STROY through Salemdom?

Choose a residential complex from our catalog and submit a request: a Salemdom broker will confirm availability and pricing, verify the developer via the official registry, and assist you with mortgages and the closing process. Get a free double mattress when you purchase an apartment through a Salemdom broker.

Methodology: monthly sales are the increase in the "sold" field in the register for projects that were in the register at the start of the month. Decreases (cancellations, corrections) are shown separately. If a developer temporarily reset the number sold to zero and restored it the following month, this counts neither as sales nor as cancellations. New projects are those that entered the register during the month; sales already recorded when they entered the register are not included in the month's sales. Sell-through and remaining stock are as of the end of the month.

Other developers

BI Group · My Home · ULYTAU Group · BAZIS-A · Stroy Opt · Sensata Group · Via Strоy Construction · Ahsel · OKSD · TUMAR Group · Atamura Group · Turan Kurylis NS · MERIDIAN stroy LTD · Beles Holding · EKM COMPANY · Kanfar Building · PARASAT CAPITAL · Kapital Stroy Kontrakt · RAMS · NAK · KazSMU · Zhetisu Residential Complex