#Developers

Tau Development developer digest: July 2026

July 2026 for Tau Development: 5 apartments sold. Sales by residential complex and city, new projects, completion dates, remaining stock and ranking among developers per the state register of shared-equity construction.

Key takeaways

Supply runway

Unsold apartments in the register: 379. At this month’s pace, they would last about 76 months.

Share of national sales

Tau Development accounts for 0.2% of the net increase in new-build sales across Kazakhstan.

Protection schemes

100% of Tau Development’s projects are being built with second-tier bank participation (BVU), 0% with a KHC guarantee and 0% under an akimat permit (MIO).

Salemdom AI commentary

Monthly Highlights

In July 2026, Tau Development recorded 5 sold apartments in the state register of shared-equity construction. In the overall July ranking by new sales, the developer placed 30th among 44 companies. Tau Development's share of the net increase in new-build sales across Kazakhstan was 0.2%, and in Almaty the company accounted for 1% of new sales.

Who was selling

All of the month’s deals took place in a single project. The leader was White Residence in Nauryzbay district, where 5 apartments were sold. The complex’s sell-through currently stands at 59%, with 77 of 190 apartments still on sale.

Supply: new objects and remaining stock

No new projects entered the register during the month; Tau Development has 10 projects listed in total. 379 unsold apartments remain on sale, enough for about 76 months at the current pace. Most of the month’s sales were in the comfort class (+5), and 2-bedroom apartments make up the largest share of supply, at 44 units.

Risks and what to check

Buyers should pay attention to completion dates: the nearest planned completion, for White Residence, is scheduled for February 2027. Buyer protection schemes are distributed as follows: 100% of Tau Development’s projects are being built with second-tier bank participation (BVU), 0% with a KHC guarantee and 0% under an akimat permit (MIO). Sales in July were uneven, peaking from 20 to 26 July (+3).

Takeaway for buyers and investors

For investors and buyers, Tau Development is a company with about 9 years of experience and a Salemdom score of 67.2 out of 100. The widest choice of layouts is currently in 2-bedroom apartments, while 3-bedroom units are 79% sold. White Residence remains the option that combines BVU protection with a choice of layouts.

Commentary prepared by Salemdom AI strictly from the issue's figures.

Monthly Highlights

For July 2026, according to the state register of shared-equity construction, Tau Development marked 5 apartments as sold.

Tau Development has 10 projects in the register (7 residential complexes): 580 apartments, of which 201 sold (35%), with 379 still on sale.

No new properties have been added to the registry this month.

Tau Development in the developer ranking

By new sales in July 2026, Tau Development ranks 30th among 44 developers with sales in the register.

Tau Development’s share of the net increase in new-build sales in Kazakhstan: 0.2%. In the brand’s main city (Almaty), it accounted for 1% of new sales.

Salemdom score based on state register facts: 67.2 out of 100; 10 projects in the register in total, the first one about 9 years ago. The score is calculated from state register facts: scale, experience, timelines, demand, transparency and supervision; the BVU, KHC and MIO schemes are treated as equal.

Sales dynamics

Weekly sales were uneven, peaking on 20–26 July (+3). Developers often record deals in batches, so weekly spikes reflect the rhythm of register updates, not just demand.

WeekNet sales growth
July 5–12+1
July 13–190
July 20–26+3
July 27–31+1

Tau Development’s best-selling residential complexes

Ranking by the increase in sold apartments in the register for July 2026. These are deals the developer has recorded in the register — the contract date and the recording date may differ by a few days.

ЖКDeveloperDistrictSold this monthRemaining
White ResidenceTau DevelopmentNauryzbai district+577

Sales leaders: details

1. White Residence (Tau Development), Nauryzbay district: +5 apartments over the month. Sell-through: 59%, with 77 of 190 still on sale. Scheme: BVU. Registered class: comfort. Nearest planned completion: February 2027.

New listings

No new Tau Development projects were added to the register in July 2026.

Homebuyer protection schemes

100% of Tau Development’s projects are being built with second-tier bank participation (BVU), 0% with a Kazakhstan Housing Company (KHC) guarantee and 0% under an akimat permit (MIO). New sales this month: BVU — 5, KHC — 0, MIO — 0.

SchemePropertiesNet sales growth
Bank involvement (Second-tier banks)10+5
KZHIK Guarantee00
Akimat (local executive body) permit00

Housing classes

By registered class, most of Tau Development’s projects are comfort (5 projects). Most of this month’s sales were in the comfort class: +5. The registered class is set by the developer under the state comfort standard; the marketing class used in a complex’s advertising may differ.

ClassPropertiesNet sales growthApartments remaining
Comfort Class5+591
Business class20288

Room count: sold and remaining

Most of Tau Development’s unsold apartments are 2-bedroom: 44. 3-bedroom apartments are selling fastest: 79% sold. Room data is from the register as of 10 October 2026; area is the typical range across projects (the median and the middle half of projects around it), excluding input errors.

RoomsApartmentsSoldRemainingSold-out rateTypical area
173492467 %59 m² (56.3–59)
2125814465 %85 m² (85–89.1)
385671879 %102.1 m² (100.6–111.7)
486275 %—
5+110100 %—

With bank participation and wide choice of apartments

Tau Development residential complexes under the BVU scheme (equity holders’ money goes through a bank) with at least 50 apartments still on sale and sales this month. This combines buyer protection with a choice of layouts.

ЖКDeveloperSold this monthSold-out rateRemaining
White ResidenceTau Development+559 %77

Frequently asked questions

How many apartments did Tau Development sell in July 2026?

According to the state register of shared-equity construction, Tau Development marked 5 apartments as sold.

Which Tau Development residential complexes sold best in July 2026?

White Residence — +5. Figures show the increase in apartments sold in the register over the month.

Which new Tau Development residential complexes appeared in July 2026?

No new properties were added to the registry in July 2026.

How many Tau Development apartments are still on sale?

According to the register, 379 of 580 apartments remain unsold (sell-through 35%). At this month’s pace, the remaining stock would last about 76 months.

Which Tau Development new builds are due for completion by the end of the year?

The register lists no Tau Development projects with a planned completion date before the end of the year.

What share of Tau Development new builds is being built with bank participation?

100% of projects involve a second-tier bank, 0% have a KHC guarantee and 0% are built under an akimat permit. The scheme for each residential complex is listed on its page under “Guarantees”.

Have any new unscrupulous-developer entries appeared for Tau Development?

No new entries for Tau Development appeared in the official list of unscrupulous developers in July 2026.

Where does the digest data come from?

From the state register of shared construction (homeportal.kz). Salemdom saves a full snapshot of the register daily; this digest compares snapshots from July 4, 2026, and July 31, 2026. Prices are sourced from developers' catalogs on Salemdom.

How do I buy a new-build apartment from Tau Development through Salemdom?

Choose a residential complex from our catalog and submit a request: a Salemdom broker will confirm availability and pricing, verify the developer via the official registry, and assist you with mortgages and the closing process. Get a free double mattress when you purchase an apartment through a Salemdom broker.

Methodology: monthly sales are the increase in the "sold" field in the register for projects that were in the register at the start of the month. Decreases (cancellations, corrections) are shown separately. If a developer temporarily reset the number sold to zero and restored it the following month, this counts neither as sales nor as cancellations. New projects are those that entered the register during the month; sales already recorded when they entered the register are not included in the month's sales. Sell-through and remaining stock are as of the end of the month.

Other developers

BI Group · Shar-Kurylys · My Home · BAZIS-A · OKSD · Beles Holding · SDN · ULYTAU Group · Sensata Group · Stroy Opt · PARASAT CAPITAL · Kanfar Building · Turan Kurylis NS · Ahsel · EKM COMPANY · БК-СТРОЙ · MERIDIAN stroy LTD · Kapital Stroy Kontrakt · Via Strоy Construction · NAK · Asyl Park · RAMS · TUMAR Group · Atamura Group

Read also

All news →