94 apartments sold
Over the month, developers marked 94 apartments as sold. BI Group sold the most: 63 % of new sales. 4 new projects with 355 apartments went on sale. 4 projects are scheduled for commissioning by the end of the year.
Buyers are not concentrated in a few complexes: the three best-selling residential complexes (Dream City Family - F, КТК/МЖК Parasat 2 III, ALTAI CITY) accounted for 47 % of new sales. In total, 17 projects had sales.
BI Group: 63 % of new sales in Turksib district of Almaty; a single developer sold more than half of all apartments.
In 1 project, the number of sold apartments decreased by 1 in total. These are cancelled contracts or corrections in the registry. So net of cancellations, 93 were sold, not 94.
The register has 3 153 unsold apartments. At this month's sales pace, they will last about 34 months, or roughly 3 years.
4 projects with 355 apartments went on sale, 3,8 times more than were sold during the month (94).
Turksib district of Almaty accounted for 2,7 % of all new-build sales in Kazakhstan for the month.
53 % of apartments in Almaty's Turksib district are sold, above the national average (46 %).
4 projects with 803 apartments are scheduled for commissioning by the end of the year; 346 of their apartments are still available. Buyers of such apartments get their keys sooner, but the developer may postpone the date.
75 % of projects in Almaty's Turksib district are built with bank participation (BVU), 22 % with a KHC guarantee, 3 % under an akimat permit (MIO). All three schemes are provided for by law.
In October 2026, developers in Almaty's Turksib district marked 94 apartments as sold, but in 1 project the number of sold apartments decreased by 1, giving net growth of +93. This is a positive trend compared with September 2026, when net growth was −50. The district accounted for 2.7 % of all new-build sales in Kazakhstan for the month.
Demand was spread across 17 projects, with BI Group as the leader, providing 63 % of new sales. The highest activity was recorded at three complexes: Dream City Family - F, КТК/МЖК Parasat 2 III and ALTAI CITY, which accounted for 47 % of new sales. Of these, Dream City Family - F showed the highest growth: +19 apartments.
Supply was replenished by 4 projects with 355 apartments. The register still holds 3 153 unsold apartments, most of them in the economy class (26 projects). By room count, two-room apartments are the most numerous on sale (1 066), while one-bedroom apartments are 63 % sold.
Buyers should check commissioning dates: by the end of the year, they are expected for 4 projects with 803 apartments, where 346 units are still available, but the developer may postpone these dates. Projects in the district are built under three legal schemes: 75 % with bank participation (BVU), 22 % with a KHC guarantee and 3 % under an akimat permit (MIO).
For investors and buyers, the district looks attractive: overall sell-through here is 53 %, above the national average (46 %). When choosing, pay attention to projects with a high degree of readiness or those that combine the BVU scheme with a wide choice of layouts, to avoid a shortage of suitable options.
Commentary prepared by Salemdom AI strictly from the issue's figures.
From 1 October to 31 October 2026, in Turksib District, Almaty, according to the KHC shared-construction registry, developers marked 94 apartments as sold; for 1 project the number of sold apartments decreased by 1; net increase — +93, about 5 625 m² of housing sold.
In total, the register has 32 projects — 27 residential complexes from 7 developers: 6 736 apartments, of which 3 583 are sold (53 %) and 3 153 remain on sale.
4 properties were added to the registry this month.
For September 2026, the net sales increase in Turksib District, Almaty was −50 (gross — 80); for October 2026 — +93 (gross — 94). The comparison is based on the same projects that were in the registry in both months.
Sales were uneven across the weeks: the most came on 22–31 October (+73). Developers often record deals in batches, so weekly spikes reflect the pace of registry updates as well as demand.
| Week | Sold net of cancellations |
|---|---|
| 1–7 October | +12 |
| 8–14 October | +2 |
| 15–21 October | +6 |
| 22–31 October | +73 |
Ranking by increase in apartments sold in the registry for October 2026. These are transactions the developer recorded in the registry — the contract date and the recording date may differ by several days.
| Residential complex | Developer | Properties | Sold this month | Remaining |
|---|---|---|---|---|
| Dream City Family - F | BI Group | 1 | +19 | 4 |
| Parasat 2 III Residential Complex | PARASAT CAPITAL | 1 | +14 | 148 |
| ALTAI CITY | Dial Group | 1 | +11 | 292 |
| Dream City Family - L | BI Group | 1 | +7 | 60 |
| Dream City Family M | BI Group | 1 | +6 | 75 |
| Dream City Eco F | BI Group | 1 | +6 | 145 |
| Dream City Eco - E | BI Group | 1 | +5 | 45 |
| JAN DOSTAR | BAZIS-A | 1 | +4 | 340 |
| Dream City Family - G | BI Group | 1 | +4 | 6 |
| Dream City Eco - C | BI Group | 1 | +3 | 14 |
1. Dream City Family - F (BI Group) — +19 apartments in the month. Share sold — 98 %, 4 of 206 still on sale. Scheme: BVU. Registry class: economy. Nearest planned commissioning — June 2027.
2. КТК/МЖК Parasat 2 III (PARASAT CAPITAL) — +14 apartments in the month. Share sold — 83 %, 148 of 852 still on sale. Scheme: KHC. Registry class: economy. Planned commissioning date has passed (August 2026).
3. ALTAI CITY (Dial Group) — +11 apartments for the month. Sold share: 33%, 292 of 434 remain on sale. Scheme: KHC. Registry class: economy. Nearest planned commissioning: March 2027.
4. Dream City Family - L (BI Group) — +7 apartments in the month. Share sold — 78 %, 60 of 271 still on sale. Scheme: BVU. Registry class: compact. Nearest planned commissioning — April 2027.
5. Dream City Family M (BI Group) — +6 apartments in the month. Share sold — 42 %, 75 of 130 still on sale. Scheme: BVU. Registry class: economy. Nearest planned commissioning — March 2027.
BI Group — 63% of the month's new sales, followed by PARASAT CAPITAL and Dial Group. The developer's place in the overall ranking and its guarantees are on the brand page.
BI Group: Salemdom score 78.9 out of 100, 537 projects in the registry in total, about 10 years in the equity construction market.
PARASAT CAPITAL: Salemdom score 70.9 out of 100, 7 projects in the registry in total, on the equity construction market for about 7 years.
Dial Group: Salemdom score 33.5 out of 100, 1 project in the registry in total, on the equity construction market for about 1 year.
| Developer | Total listings | Sold this month | Share of new sales |
|---|---|---|---|
| BI Group | 19 | +59 | 63 % |
| PARASAT CAPITAL | 3 | +17 | 18 % |
| Dial Group | 1 | +11 | 12 % |
| BAZIS-A | 1 | +4 | 4 % |
| Everest Development | 1 | +2 | 2 % |
During the month, 4 projects with 355 apartments entered the KHC shared-construction registry in Turksib District, Almaty. Entering the registry means that the developer has received permission to raise buyers’ funds and can officially sell apartments during the construction stage.
| Residential complex | Developer | Scheme | Apartments | Scheduled completion |
|---|---|---|---|---|
| Tumanbay Moldagalyev (phase 2) | KazSMU | BVU | 110 | January 2028 |
| Tumanbay Moldagalyev (phase 1) | KazSMU | BVU | 105 | January 2028 |
| Tumanbay Moldagalyev (phase 3) | KazSMU | BVU | 70 | January 2028 |
| Tumanbay Moldagalyev (phase 4) | KazSMU | BVU | 70 | January 2028 |
In October 2026, the planned commissioning date fell for 2 projects.
By the end of the year, the deadline falls due for 4 more project with 803 apartments, of which 346 are unsold. Nearest:
| Residential complex | Developer | Scheduled completion | Apartments | Not sold |
|---|---|---|---|---|
| Dream City Eco - C | BI Group | November 2026 | 309 | 14 |
| Dream City Family N | BI Group | November 2026 | 99 | 34 |
| Atmosphere (Phase 6) | Atamura Group | December 2026 | 170 | 103 |
| Turar | Everest Development | December 2026 | 225 | 195 |
75 % of projects in Almaty's Turksib district are built with bank participation (BVU), 22 % with a guarantee from the Kazakhstan Housing Company (KHC), 3 % under an akimat permit (MIO). New sales for the month: BVU 63, KHC 28, MIO 2.
| Scheme | Properties | Net sales growth |
|---|---|---|
| Bank involvement (Second-tier banks) | 24 | +63 |
| KZHIK Guarantee | 7 | +28 |
| Akimat (local executive body) permit | 1 | +2 |
By the class stated in the register, most projects in Almaty's Turksib district are economy (26 projects). The most sales this month were in the economy class: +70. The class in the register is set by the developer under the state comfort standard; the marketing class in a residential complex's advertising may differ.
| Class | Properties | Net sales growth | Apartments remaining |
|---|---|---|---|
| Economy class | 26 | +70 | 2 683 |
| Compact | 6 | +23 | 470 |
The largest pool of unsold apartments in Almaty's Turksib district is two-room units: 1 066. One-bedroom apartments sell fastest: 63 % sold. Room-count data are from the register as of 16 November 2026; floor area is the typical range across projects (the median and the half of projects around it), excluding input errors.
| Rooms | Apartments | Sold | Remaining | Sold-out rate | Typical area |
|---|---|---|---|---|---|
| 1 | 2 214 | 1 401 | 813 | 63 % | 41 m² (36.1–45) |
| 2 | 2 558 | 1 492 | 1 066 | 58 % | 59.6 m² (56.7–61.7) |
| 3 | 1 271 | 761 | 510 | 60 % | 82.4 m² (79.4–85.9) |
| 4 | 267 | 111 | 156 | 42 % | 104.4 m² (97.5–118.3) |
Residential complexes in the Turksib district of Almaty, where over 80% of apartments have been sold and sales continued this month. Only a few units remain—if you find a suitable layout, we recommend making a decision without delay.
| Residential complex | Developer | Sold this month | Sold-out rate | Remaining |
|---|---|---|---|---|
| Dream City Family - F | BI Group | +19 | 98 % | 4 |
| Parasat 2 III Residential Complex | PARASAT CAPITAL | +14 | 83 % | 148 |
| Dream City Family - G | BI Group | +4 | 97 % | 6 |
| Dream City Eco - C | BI Group | +3 | 95 % | 14 |
| Dream City Family - E | BI Group | +3 | 89 % | 20 |
A residential complex in the Turksib district of Almaty with a bank-controlled payment scheme (escrow accounts), where at least 50 apartments are still available and sales have continued this month. This offers a combination of buyer protection and a wide variety of floor plans.
| Residential complex | Developer | Sold this month | Sold-out rate | Remaining |
|---|---|---|---|---|
| Dream City Family - L | BI Group | +7 | 78 % | 60 |
| Dream City Family M | BI Group | +6 | 42 % | 75 |
| Dream City Eco F | BI Group | +6 | 22 % | 145 |
| JAN DOSTAR | BAZIS-A | +4 | 23 % | 340 |
| Dream City Eco - D | BI Group | +2 | 63 % | 69 |
| Dream City Eco G | BI Group | +2 | 34 % | 117 |
According to the Salemdom catalog as of 14 October 2026: 5 residential complexes with open prices, the most affordable apartment starts from 21,3 million ₸, and the median starting price across residential complexes is 34,7 million ₸.
The price in the digest represents the starting price of an apartment in the residential complex (the cheapest available unit), rather than the average transaction price. Salemdom has been tracking price history for this complex since September 20, 2026, so monthly dynamics are not shown.
According to the KHC shared-construction registry, developers marked 94 apartments as sold; for 1 project the number of sold apartments decreased by 1, net increase — +93. That is about 5 625 m² of housing.
Dream City Family - F — +19; КТК/МЖК Parasat 2 III — +14; ALTAI CITY — +11; Dream City Family - L — +7; Dream City Family M — +6. The figures show the increase in sold apartments in the registry over the month.
BI Group — +59; PARASAT CAPITAL — +17; Dial Group — +11; BAZIS-A — +4; Everest Development — +2. The leader accounted for 63% of new sales.
4 projects with 355 apartments entered the registry: Tumanbay Moldagalyev (phase 2) (KazSMU), Tumanbay Moldagalyev (phase 1) (KazSMU), Tumanbay Moldagalyev (phase 3) (KazSMU), Tumanbay Moldagalyev (phase 4) (KazSMU).
According to the register, 3 153 of 6 736 apartments are unsold (sell-through 53 %). At this month's pace, the remaining stock will last about 34 months.
The planned commissioning date falls due for 4 projects with 803 apartments: Dream City Eco - C — November 2026; Dream City Family N — November 2026; Атмосфера (phase 6) — December 2026; Turar — December 2026. The dates are planned; the developer may extend them.
75 % of projects are built with second-tier bank participation, 22 % with a KHC guarantee, 3 % under an akimat permit. The scheme of each residential complex is shown on its page in the “Guarantees” section.
According to the Salemdom catalog as of 14 October 2026, the most affordable apartment starts from 21,3 million ₸, and the median starting price across 5 residential complexes is 34,7 million ₸. Prices for each residential complex are in the catalog.
No new entries appeared in the official list of unscrupulous developers in Turksib District, Almaty in October 2026.
From the shared-construction registry of Kazakhstan Housing Company (KHC). Salemdom saves a full snapshot of the registry every day; the digest compares the snapshots as of 30 September 2026 and 31 October 2026. From 27 October 2026 to 2 November 2026, the registry showed a doubled number of sold apartments for 12 projects and then corrected it — for them, the value after correction (3 November 2026) is used. Prices are from developers' catalogs on Salemdom.
Choose a residential complex from our catalog and submit a request: a Salemdom broker will confirm availability and pricing, verify the developer via the official registry, and assist you with mortgages and the closing process. Get a free double mattress when you purchase an apartment through a Salemdom broker.
How we calculated: monthly sales are the increase in the “sold” field in the register for projects that were in the register at the start of the month. Decreases (cancellations, corrections) are shown separately. If a developer temporarily reset the number sold to zero and restored it the following month, this counts as neither sales nor cancellations. New projects are those that appeared in the register during the month; their sales at the time of entering the register are not included in monthly sales. Sell-through and unsold stock are as of the end of the month, excluding archived register records: if the planned commissioning date passed more than half a year ago and there is not a single contract, equity raising under the record is closed and it is not counted in unsold stock.