September 2026 at Atamura Group: 14 apartments sold, 1 new project in the register, 3 projects due for completion by the end of the year. Sales by residential complex and city, new projects, completion dates, remaining stock and place among developers based on data from the state register of shared-equity construction.
According to the register, 805 apartments are unsold. At this month's pace, they will last about 58 months.
1 project with 67 apartments entered the register — more than were sold during the month (14).
Atamura Group — 0.6% of the net increase in new-build sales in Kazakhstan.
By the end of the year, the planned completion date falls due for 3 projects with 428 apartments; 259 of them are still unsold. Buyers of such apartments get their keys sooner, but the developer may extend the deadlines.
0% of Atamura Group projects are built with bank participation (BVU), 46% with a KHC guarantee, and 54% under an akimat permit (MIO).
In September 2026, Atamura Group marked 14 apartments as sold, about 764 m² of housing. Compared with August 2026, when the net sales increase was +18, activity declined. In the overall ranking of developers by new sales, the company moved from 13th to 18th place out of 43. Atamura Group's share of the net increase in new-build sales in Kazakhstan was 0.6%.
Most of the month's deals were in Almaty, where +9 sales were recorded. The leader was Atmosfera in Turksib district (+9 apartments), followed by Keruen (+5 apartments). Talgar district also recorded +5 sales. There were no new deals in Karasai district, but the developer expanded its presence there.
Atamura Group currently has 13 projects in the register, 11 in the economy class and 2 in the comfort class. 1 new project entered during the month: Aqsai Resort (phase 1) with 67 apartments. In total, 805 apartments remain on sale, which at the current pace will last about 58 months. 2-bedroom apartments make up the largest share of remaining stock, at 327 units.
Buyers should pay attention to completion dates: by the end of the year, the planned completion date falls due for 3 projects with 428 apartments, 259 of which are still unsold. Equity holder protection schemes are split as follows: 46% of projects are built with a KHC guarantee, 54% under an akimat permit (MIO), and 0% with bank participation (BVU). The developer may extend completion dates.
For investors and buyers, Atamura Group is a company with about 4 years of experience and a Salemdom score of 55.9 out of 100. The fastest access to keys is currently possible in projects with planned completion in October and December 2026. When choosing an apartment, consider the actual housing class in the register and the protection scheme.
Commentary prepared by Salemdom AI strictly from the issue's figures.
From September 1 to September 30, 2026, according to the state register of shared-equity construction, Atamura Group marked 14 apartments as sold, about 764 m² of housing.
У Atamura Group в реестре 13 объектов — 5 ЖК: 1 114 квартир, из них продано 309 (28 %), в продаже остаётся 805.
1 property was added to the registry this month.
By new sales in September 2026, Atamura Group ranks 18th among 43 developers with sales in the register; a month earlier it was 13th.
Atamura Group's share of the net increase in new-build sales in Kazakhstan is 0.6%. In the brand's main city (Almaty), it accounted for 2% of new sales.
Salemdom score based on state register facts: 55.9 out of 100; 13 projects in the register in total, the first one about 4 years ago. The score is based on register facts: scale, experience, timelines, demand, transparency and oversight; the BVU, KHC and MIO schemes count equally.
In August 2026, Atamura Group's net sales increase was +18 (gross 18); in September 2026 it was +14 (gross 14). The comparison covers the same projects that were in the register in both months.
Sales were uneven week to week: the peak was September 1–7 (+5). Developers often record deals in batches, so weekly spikes also reflect how they work with the register, not just demand.
| Week | Net sales growth |
|---|---|
| September 1–7 | +5 |
| September 8–14 | +5 |
| September 15–21 | +3 |
| September 22–30 | +1 |
Ranking by the growth of apartments sold in the registry for September 2026. These are transactions recorded by the developer in the registry; please note that the contract date and the registry entry date may differ by a few days.
| ЖК | Developer | District | Sold this month | Remaining |
|---|---|---|---|---|
| Atmosphere | Atamura Group | Turksib | +9 | 298 |
| Keruen | Atamura Group | — | +5 | 259 |
1. Atmosfera (Atamura Group), Turksib district — +9 apartments for the month. Sell-through 39%, 298 of 490 still on sale. Scheme: KHC. Register class: economy. Nearest planned completion: October 2026.
2. Keruen (Atamura Group) — +5 apartments for the month. Sell-through 26%, 259 of 352 still on sale. Scheme: MIO. Register class: economy, comfort. Nearest planned completion: October 2026.
During the month, 1 Atamura Group project with 67 apartments entered the register of shared-equity construction. Entry into the register means the developer has received permission to raise equity holders' funds and can officially sell apartments during construction.
| ЖК | Developer | Scheme | Apartments | Scheduled completion |
|---|---|---|---|---|
| Aqsai Resort (Phase 1) | Atamura Group | МИО | 67 | December 2029 |
As of September 2026, there were no scheduled completion dates.
By the end of the year, the date falls due for another 3 projects with 428 apartments, 259 of them unsold. The nearest:
| ЖК | Developer | Scheduled completion | Apartments | Not sold |
|---|---|---|---|---|
| Keruen (Phase 4) | Atamura Group | October 2026 | 88 | 66 |
| Atmosphere (Phase 5) | Atamura Group | October 2026 | 170 | 90 |
| Atmosphere (Phase 6) | Atamura Group | December 2026 | 170 | 103 |
0% of Atamura Group projects are built with bank participation (BVU), 46% with a guarantee from KHC (Kazakhstan Housing Company), and 54% under an akimat permit (MIO). New sales this month: BVU — 0, KHC — 9, MIO — 5.
| Scheme | Properties | Net sales growth |
|---|---|---|
| Bank involvement (Second-tier banks) | 0 | 0 |
| KZHIK Guarantee | 6 | +9 |
| Akimat (local executive body) permit | 7 | +5 |
By the class stated in the register, most Atamura Group projects are economy (11 projects). Most of the month's sales were in the 'economy' class: +9. The register class is set by the developer according to the national comfort standard; the marketing class in a complex's advertising may differ.
| Class | Properties | Net sales growth | Apartments remaining |
|---|---|---|---|
| Economy class | 11 | +9 | 651 |
| Comfort Class | 2 | +5 | 154 |
Most of Atamura Group’s unsold apartments are 2-bedroom: 327. 2-bedroom apartments are selling fastest: 35% sold. Room data is from the register as of 10 October 2026; area is the typical range across projects (the median and the middle half of projects around it), excluding input errors.
| Rooms | Apartments | Sold | Remaining | Sold-out rate | Typical area |
|---|---|---|---|---|---|
| 1 | 301 | 85 | 216 | 28 % | 44.5 m² (37.8–45) |
| 2 | 501 | 174 | 327 | 35 % | 58.7 m² (49.5–59.2) |
| 3 | 216 | 51 | 165 | 24 % | 78.2 m² (78.2–82.8) |
| 4 | 39 | 0 | 39 | 0 % | — |
| 5+ | 28 | 0 | 28 | 0 % | — |
| City | Properties | Net sales growth | New objects | Sold-out rate | Remaining |
|---|---|---|---|---|---|
| Almaty | 3 | +9 | 0 | 39 % | 298 |
| Talgar District | 8 | +5 | 0 | 21 % | 440 |
| Talgar | 1 | 0 | 0 | — | 0 |
| Karasay District | 1 | 0 | 1 | 0 % | 67 |
According to the state register of shared-equity construction, Atamura Group marked 14 apartments as sold. That is about 764 m² of housing.
Atmosfera — +9; Keruen — +5. Figures show the monthly increase in sold apartments in the register.
1 project with 67 apartments entered the register: Aqsai Resort (phase 1) (Atamura Group).
По реестру не продано 805 квартир из 1 114 (распроданность 28 %). При темпе этого месяца остатка хватит примерно на 58 месяцев.
The planned completion date falls due for 3 projects with 428 apartments: Keruen (phase 4) — October 2026; Atmosfera (phase 5) — October 2026; Atmosfera (phase 6) — December 2026. These dates are planned; the developer may extend them.
0% of projects are built with second-tier bank participation, 46% with a KHC guarantee, and 54% under an akimat permit. Each residential complex's scheme is shown on its page in the 'Guarantees' section.
No new entries for Atamura Group appeared in the official list of unscrupulous developers in September 2026.
From the state register of shared construction (homeportal.kz). Salemdom saves a complete snapshot of the register daily; this digest compares snapshots from August 31, 2026, and September 30, 2026. Prices are sourced from developers' catalogs on Salemdom.
Choose a residential complex from our catalog and submit a request: a Salemdom broker will confirm availability and pricing, verify the developer via the official registry, and assist you with mortgages and the closing process. Get a free double mattress when you purchase an apartment through a Salemdom broker.
Methodology: monthly sales are the increase in the "sold" field in the register for projects that were in the register at the start of the month. Decreases (cancellations, corrections) are shown separately. If a developer temporarily reset the number sold to zero and restored it the following month, this counts neither as sales nor as cancellations. New projects are those that entered the register during the month; sales already recorded when they entered the register are not included in the month's sales. Sell-through and remaining stock are as of the end of the month.
BI Group · BAZIS-A · My Home · ULYTAU Group · NAK · Sensata Group · Beles Holding · Stroy Opt · TUMAR Group · Orda Invest · EKM COMPANY · Via Strоy Construction · Kanfar Building · Turan Kurylis NS · MERIDIAN stroy LTD · RAMS · OKSD · Ahsel · PARASAT CAPITAL · Kapital Stroy Kontrakt · Asyl Park · БК-СТРОЙ · KazSMU · Shar-Kurylys