Логотип TUMAR GroupTUMAR Group — developer: residential complexes, guarantees and deadlines from the state register

Developer TUMAR Group: 13 shared-equity construction projects in the state register (Astana — 10, Ust-Kamenogorsk — 2, Shymkent — 1), since 2017. BVU/KHC/MIO schemes 3/2/8…

TUMAR Group residential complexes on Salemdom

Astana · 7

East Kazakhstan Region · 2

Shymkent · 1

Registered Legal Entities

  • TUMAR Group LLP — БИН 040540018865
  • ТОО "Comfort-Uly Dala" — БИН 190940009528
  • ТОО "Алан Строй Групп" — БИН 210540010632

Score breakdown

  • Scale: 14.3 out of 25
  • Experience: 15 of 15
  • Registration deadlines: 5.6 out of 20
  • Demand: 2.2 out of 20
  • Transparency: 3.7 out of 12
  • Supervision: 8 out of 8

How the score is calculated

The score from 0 to 100 is made up of six components, each calculated solely from facts in the state register of shared-equity construction (homeportal.kz). Reviews, advertising and opinions are not taken into account. The equity holder protection schemes — BVU, KHC and MIO — are equally valid: all three are provided for by law, so the scheme does not affect the score. The weights are published so they can be discussed. Brands with a single project in the register are not ranked, as a score based on one building is unreliable.

ComponentMax.Materials
Scale25Number of listings in the registry
Experience15years from the start of construction (8 years = maximum)
Registry deadlines20доля объектов с наступившим плановым сроком ввода; минус, если срок прошёл, а прогресс < 100 %
Demand20Sold-out rate according to registry data
Transparency12photos, residential complex website, and KZhK monitoring report
Supervision8Managed by an authorized or supervisory company
Penalty-30%The legal entity is on the official blacklist of unreliable developers.

Frequently asked questions

Is TUMAR Group a reliable developer?

Reviews are subjective, so we look at the facts from the state register of shared-equity construction. Salemdom score based on register facts: 48.8 out of 100. With bank participation: 3 of 13 projects; with a KHC guarantee: 2; under an akimat permit: 8. None of the brand's legal entities are on the list of unscrupulous developers.

How many projects does TUMAR Group have in the state register?

13 shared-equity construction projects — 10 residential complexes (Astana — 10, Ust-Kamenogorsk — 2, Shymkent — 1). A project in the register is a separate phase or block with its own permit to raise equity holders' funds, so there are more projects than residential complexes.

In which cities does TUMAR Group build?

According to the state register, TUMAR Group builds in 3 cities: Astana — 10, Ust-Kamenogorsk — 2, Shymkent — 1. In Astana, most of its projects are in these districts: Yesil — 4, Nura — 2, Almaty — 1.

How long has TUMAR Group been on the market?

TUMAR Group's first project in the state register of shared-equity construction was started in 2017 — about 9 years ago. Only projects financed with equity holders' money are counted; buildings completed before the register existed or built with the developer's own funds are not included.

Which TUMAR Group residential complexes are on Salemdom?

Salemdom lists 10 residential complexes by TUMAR Group: Athletic City (Astana), Tumar Residence (Astana), Uly Dala Park (Astana), ATHLETIC (Astana), Sultan Beibarys (Astana), Tumar Club (Astana), Altyn Uya (Astana), Beibarys Residence (Shymkent) and others. Each page shows register data, the completion date, the location and, where the developer has opened sales, apartment layouts and prices.

Which TUMAR Group residential complexes are under construction now, and when is completion?

Nearest planned completion dates in the register: Athletic City — October 2026; Tumar Club — November 2026; Tumar Residence — January 2027; Sultan Beibarys — February 2027. In total, 6 residential complexes on the site are listed as "under construction". The dates are planned ones, taken from the permit to raise funds; the developer may extend them.

Does TUMAR Group complete buildings on time?

Of 13 projects with a completion date, 4 have already reached the planned date. The register does not yet contain any commissioning certificates. The register reflects certificates with a delay, so it is best to confirm the acceptance status of a specific building — leave a request on Salemdom and we will check.

Does TUMAR Group have overdue projects?

According to the register, 1 TUMAR Group project has passed the planned date while construction readiness is below 100%. This lowers the deadlines score in the rating. Before buying in such a building, check whether the permit has been extended and which scheme protects equity holders' money.

Which equity holder protection schemes does TUMAR Group use?

According to the register: second-tier bank (BVU) participation — 3 projects, KHC (Kazakhstan Housing Company) guarantee — 2, local executive body (MIO / akimat) permit — 8. With bank participation, equity holders' money goes through the bank under its control; a KHC guarantee means the building will be completed if the developer runs into problems; an akimat permit is issued after the building's frame has been erected. All three schemes are provided for by law.

Can I buy a TUMAR Group apartment with bank participation (escrow)?

Yes: 3 of 13 TUMAR Group projects (23%) use the second-tier bank scheme, compared with 61% on average across the register. The scheme is shown on each residential complex page on Salemdom, in the "Guarantees" section.

How many TUMAR Group apartments have been sold?

По реестру у застройщика 2 300 квартир, продано 255 — 11 %. Данные о продажах есть по 11 из 13 объектов; распроданность заполняет сам застройщик, поэтому цифры могут отставать.

How can I find out TUMAR Group apartment prices?

TUMAR Group does not yet have an open catalog of apartments with prices on Salemdom. Leave a request on Salemdom — a broker will confirm availability, prices and installment or mortgage terms for the residential complex you need.

Is TUMAR Group on the list of unscrupulous developers?

No: TUMAR Group's legal entities are not on the official list of unscrupulous developers. We check by BIN at every register update.

Where does TUMAR Group rank among developers in Kazakhstan?

18th place in the rating of Kazakhstan developers by sales: 284 apartments sold in total across all TUMAR Group projects in the state register of shared-equity construction. The rating counts only the number of apartments sold — no opinions and no advertising. Separately, based on register facts (scale, experience, deadlines, demand, transparency, supervision), TUMAR Group has a Salemdom score of 48.8 out of 100.

Where is TUMAR Group stronger and weaker than other developers?

TUMAR Group's strongest rating components: experience — 15 of 15, supervision — 8 of 8. Weakest: demand — 2.2 of 20, register deadlines — 5.6 of 20. Each component is calculated from register facts; the scoring formula is published on the rating page.

How does TUMAR Group compare with other developers in Astana?

In Astana, 57 developers have projects in the register; by rating score, TUMAR Group ranks 26th among them. The top is BI Group (77.5). TUMAR Group has 10 projects in Astana.

How transparent is TUMAR Group?

According to the register: construction photos are available for 85% of TUMAR Group projects, a residential complex website for 8%, and a Kazakhstan Housing Company monitoring report for 0%. The more open materials a project has, the easier it is to check actual construction progress.

Who oversees TUMAR Group construction?

An authorized or supervisory company is listed in the register for 100% of TUMAR Group projects. For 2 projects with a KHC guarantee, construction progress is additionally checked by Kazakhstan Housing Company. For 3 projects with bank participation, equity holders' money is controlled by the bank.

Which TUMAR Group legal entities are in the shared-equity construction register?

ТОО «TUMAR Group» (БИН 040540018865); ТОО "Comfort-Uly Dala" (БИН 190940009528); ТОО "Алан Строй Групп" (БИН 210540010632). Объекты одного бренда часто оформлены на разные ТОО — перед сделкой сверьте БИН в договоре с реестром.

What is the largest TUMAR Group residential complex?

By the number of apartments in the register — Uly Dala Park (Astana): 506 apartments, planned completion — October 2027.

How do I check TUMAR Group before buying an apartment?

Find the project in the shared-equity construction register and check three things: the seller's BIN in the contract matches the developer's BIN in the register, the money protection scheme (bank participation, KHC guarantee or akimat permit) and the planned completion date. On Salemdom, all of this is collected in the "Guarantees" section of each TUMAR Group residential complex, which also shows whether there is an entry in the list of unscrupulous developers.

How do I buy a TUMAR Group apartment through Salemdom?

Choose a residential complex and an apartment on Salemdom and submit a request. A Salemdom broker will confirm availability and the current price, compare mortgage programs, and assist you with the transaction. Buy an apartment with a Salemdom broker and receive a double mattress as a gift.

Where does the data on TUMAR Group come from, and how often is it updated?

From the state register of shared-equity construction (homeportal.kz): project cards, protection schemes, deadlines, sales and the list of unscrupulous developers. The register is re-read at least once a week; the latest export was on October 12, 2026. Apartment prices come from the catalogs of developers connected to Salemdom.

TUMAR Group sales by month

18th place в in the Kazakhstan developer sales ranking: 284 apartments sold in total according to the state register.

MonthSoldNet changeNew objectsOverview
September 202629+281digest
August 202622+160digest
July 20261+10digest