#Comparisons

BAZIS-A or OKSD: developer comparison

Comparison of BAZIS-A and OKSD based on KHC registry facts: ranking, buyer protection schemes, on-time delivery, delays, sales from July to 31 October 2026, new projects, top residential complexes. Building together: Shymkent.

Key points

BAZIS-A and OKSD build in the same city: Shymkent (4 and 11 projects). Below are only facts from the register of shared-construction projects of KHC JSC, without reviews or advertising: rating, protection schemes, deadlines, sales, supply by room count and sales launches.

In the ranking of Kazakhstan developers by sales, BAZIS-A is 2nd (5,226 apartments sold all-time), OKSD is 7th (1,227); the Salemdom score based on registry facts is 76.4 and 73.4. From July through 31 October 2026, BAZIS-A recorded +687 sold apartments in the registry, OKSD — +82.

Salemdom AI commentary

Key points

The main difference between the developers lies in the scale of their operations and sales volumes. BAZIS-A ranks 2nd by sales with 5 226 apartments sold all-time, while OKSD is in 7th place with 1 227 apartments. The Salemdom scores based on register facts are 76 and 75 respectively. From July to October 31, 2026, BAZIS-A marked +687 sold apartments in the register, and OKSD — +82.

Where and how they sell

BAZIS-A operates in Almaty (251 projects), Astana (94), Shymkent (8) and Atyrau (3), offering mainly economy-class housing (89 projects). OKSD builds in Shymkent (25) and Ust-Kamenogorsk (1), where the comfort class prevails (10 projects). In Shymkent, BAZIS-A has 4 projects with 230 apartments unsold, OKSD has 11 projects with 512 apartments unsold. By room count, BAZIS-A has the most 2-room apartments on sale (3 061), and OKSD is also dominated by 2-room apartments (294).

Equity holder protection and deadlines

Shared-equity buyer protection is implemented through different schemes. BAZIS-A has 73 % of projects with BVU participation (259 BVU, 67 KHC, 30 MIO), OKSD has 8 % of projects (2 BVU, 24 KHC, 0 MIO). On commissioning dates, BAZIS-A has 21 on-time commissioning certificates out of 21 and 3 overdue projects. OKSD has 0 on-time commissioning certificates out of 1 and 1 overdue project.

Takeaway for buyers

When choosing a specific residential complex, rely on register data for each project. By the end of 2026, commissioning is planned for 4 BAZIS-A residential complexes (for example, КД BENELUX on November 2, 2026) and 2 OKSD residential complexes (for example, Жанұя on November 4, 2026). We recommend checking the protection scheme and actual sell-through of each complex in the Guarantees section on Salemdom.

Commentary prepared by Salemdom AI strictly from the issue's figures.

Comparison based on register facts

IndicatorBAZIS-AOKSD
Rank by sales27
Apartments sold all-time5 2261 227
Salemdom score (out of 100)76,473,4
Objects in registry36226
CitiesAlmaty (254), Astana (97), Shymkent (8), Atyrau (3)Shymkent (25), Ust-Kamenogorsk (1)
In the shared-equity market10 years7 years
With bank participation (BVU)73% of projects8% of projects
BVU / KHC / MIO schemes265 / 67 / 302 / 24 / 0
Apartments in the register, sold29 516, 21 %2 519, 44 %
Completion date reached299 of 36221 of 25
Completion certificates on time23 of 230 of 1
Overdue (readiness < 100%)11
Entries in the unscrupulous developers list00
New projects in the period122

How the rating is built

The Salemdom score is the sum of six components based on KHC registry facts. Higher by component: scale — BAZIS-A; experience — BAZIS-A; demand — OKSD; transparency — OKSD.

ComponentBAZIS-AOKSDMaximum
Scale2517,925
Experience1514,215
Registry deadlines16,516,520
Demand4,18,820
Transparency7,8812
Supervision888

Where they overlap: cities

Shymkent: BAZIS-A has 4 projects (sold over the period +2, sell-through 25 %, with a bank 100 %), OKSD has 11 projects (+135, 70 %, with a bank 18 %). 230 and 512 apartments remain on sale.

CityBAZIS-A: projectsOKSD: projectsBAZIS-A: soldOKSD: soldBAZIS-A: remainingOKSD: remaining
Shymkent411+2+135230512

Sales by month

Net increase in sold apartments in the register by month. BAZIS-A sold more over the whole period. Negative values are cancellations or data corrections.

MonthBAZIS-AOKSD
July−53+80
August+88+24
September+193+8
October+459-30%

Housing classes

BAZIS-A has the most projects in the “economy” class (89), OKSD in “comfort” (10). Class is per the state comfort standard stated in the register.

ClassBAZIS-A: projectsOKSD: projects
Comfort Class010
Economy class892

Apartments on sale by room count

How many apartments of each type are still unsold and their typical area (median across projects) — based on the latest KHC registry export.

RoomsBAZIS-A: remainingBAZIS-A: areaOKSD: remainingOKSD: floor area
12 28941.2 m²23944.1 m²
23 06161.3 m²29461.2 m²
31 54589.3 m²9984.8 m²
4359135.8 m²21121 m²
5+16220.5 m²10119.1 m²

Completion by the end of 2026

The planned commissioning date falls before year-end for 4 residential complexes of BAZIS-A (177 apartments unsold) and 2 residential complexes of OKSD (112 unsold).

BAZIS-A: КД BENELUX — 2 November 2026; GRAND MONACO — 3 December 2026; Premium complex VESPER — 4 December 2026; FORTIS — 6 December 2026.

OKSD: Жанұя — 4 November 2026; КГ KAINAR VILLAGE — 25 December 2026.

Sales launches in the period

New projects in the registry from July to 31 October 2026: BAZIS-A — 8 residential complexes (NURLY DALA 2, FORTIS, MAVERICK, ALTER, TAULAN), OKSD — 2 residential complexes (Asyl Mura, Престиж).

BAZIS-A's best-selling residential complexes

Residential complexCitySold in the periodRemainingSold-out rate
AUEZOV CITYAlmaty+12554554 %
LANDMARK GOLDAstana+825053 %
AUEZOV CITY PROAlmaty+9010170 %
ALTERAstana+7928322 %
NURLY DALA 2Almaty+221 51515 %

OKSD’s best-selling residential complexes

Residential complexCitySold in the periodRemainingSold-out rate
FamilyShymkent+7611158 %
TULPARShymkent+488065 %
Asar houseShymkent+69666 %
Prime ParkShymkent+512469 %
КГ KAINAR VILLAGEShymkent0198 %

Bottom line

Sales in the period: higher for BAZIS-A (687 vs 82).

Properties in the registry: more at BAZIS-A (362 versus 26).

Projects with bank participation (share): higher for BAZIS-A (73% vs 8%).

New projects (sales starts): more for BAZIS-A (12 vs 2).

Equal number of overdue projects: 1.

The choice depends on the specific residential complex: the protection scheme, completion date and sell-through vary greatly between complexes of the same developer. Check each residential complex in the "Guarantees" section on Salemdom — or submit a request, and a broker will compare options from both developers.

Frequently asked questions

Who is more reliable: BAZIS-A or OKSD?

Based on KHC registry facts: Salemdom score — 76.4 for BAZIS-A and 73.4 for OKSD; equity-holder protection schemes (BVU / KHC / MIO) — 265 / 67 / 30 and 2 / 24 / 0, all three equivalent under the law; overdue properties — 1 and 1; entries in the list of unscrupulous developers — 0 and 0. We do not take reviews into account.

Who has more new builds with bank participation?

At BAZIS-A: BAZIS-A has 265 BVU properties (73%), OKSD — 2 (8%). The KHC and MIO schemes are also provided for by the equity participation law.

Who completes buildings on time?

BAZIS-A: the planned date has arrived for 299 of 362 properties, on-time commissioning certificates — 23 of 23. OKSD: 21 of 25, on-time certificates — 0 of 1.

Whose apartments sell better?

From July to 31 October 2026: BAZIS-A — +687, OKSD — +82 apartments sold per the registry.

Who has more apartments on sale?

According to the register, 7 270 apartments are unsold at BAZIS-A and 663 at OKSD. Details by room count are in the table above.

Who builds more in Shymkent?

BAZIS-A — 4 projects, OKSD — 11. Sold over the period: +2 and +135.

Who has more new projects?

From July to 31 October 2026, 8 residential complexes of BAZIS-A and 2 residential complexes of OKSD entered the registry.

Where do BAZIS-A and OKSD build?

BAZIS-A: Almaty — 254, Astana — 97, Shymkent — 8, Atyrau — 3. OKSD: Shymkent — 25, Ust-Kamenogorsk — 1.

How to choose an apartment from BAZIS-A or OKSD?

Compare specific residential complexes: protection scheme, completion date, sell-through and price. A Salemdom broker will select options from both developers and check them against the register. Buy an apartment with a Salemdom broker and get a double mattress as a gift.

How we calculated: monthly sales are the increase in the “sold” field in the register for projects that were in the register at the start of the month. Decreases (cancellations, corrections) are shown separately. If a developer temporarily reset the number sold to zero and restored it the following month, this counts as neither sales nor cancellations. New projects are those that appeared in the register during the month; their sales at the time of entering the register are not included in monthly sales. Sell-through and unsold stock are as of the end of the month, excluding archived register records: if the planned commissioning date passed more than half a year ago and there is not a single contract, equity raising under the record is closed and it is not counted in unsold stock.